Resolve ownership and records first
Before physical movement, confirm mold ownership, release authorization, cavity identification and the records that must travel with the asset. The receiving team should have the latest 3D tool data, 2D drawings, steel specifications, hot-runner information, spare-parts list and approved part drawing.
Document the mold before shipment
A condition review establishes what is being transferred and prevents disputes after arrival. Photograph the mold, cavities, cores, slides, lifters, connectors, identification plates and visible wear. Record the last preventive maintenance, repair history and current cycle performance.
- Current sample and dimensional report
- Approved molding parameters
- Known flash, venting or cooling concerns
- Critical spare inserts and wear components
- Water-line and electrical diagrams
Verify destination-machine compatibility
Compare mold dimensions, weight, tie-bar spacing, platen pattern, locating ring, nozzle radius, shut height, required daylight, ejection, hydraulic or pneumatic functions and controller requirements. Cooling and electrical connections may need standardization before production can begin.
Plan the final run and first Mexico trial
Whenever possible, complete a documented final production run before the mold leaves China. Retain approved samples and process data. After arrival in Mexico, inspect the tool before installation, complete maintenance if needed, and run a structured sampling plan against the same drawing and acceptance criteria.
Revalidate the process—not only the part
A dimensional pass on a few samples does not prove long-term stability. Revalidation should establish a repeatable process window, cycle time, cavity balance, appearance, functional performance and the quality records required by the customer.